|
General
This applies specifically to pipework for water
systems, specifically heating systems, chilled water systems
and hot and cold water domestic systems, including mains water.
Flushing, cleaning and water treatment should
be carried out on all projects and pipework modification works,
unless specifically indicated as not necessary in the particular
specification.
All works comply with Statutory Authority and
HSE requirements and regulations.
The whole of our flushing, cleaning and
water treatment procedures comply fully with BSRIA Application
Guides 8/91, Pre-commissioning Cleaning of Water Systems, and
2/93, Water Treatment for Building Services Systems.
Liason is necessary to ensure that any special
requirements, such as flushing points, by-passes, dosing pots,
pockets, valves, strainers, etc, are provided to enable work
to be undertaken fully and completely. Also, information regarding
all materials used within the system and hence all the materials
that will come into contact with all cleaning and treatment
chemicals.

Mains Water Analysis
An analysys of the water is supplied which can
be checked with the local water supply authority to ensure that
the end analysis results are typical for the site area.

Method Statement
A method statement is provided including details
of works sequence, programme, chemicals and concentrations,
and any temporary or portable equipment required to complete
the works satisfactorily.
The Mechanical Contractor may then notify manufacturers
and suppliers of equipment of the proposed system cleaning and
chemical treatment processes to establish if any manufacturer
or supplier of equipment requires any particular cleaning and
chemical treatment process due to size of waterways or materials
used, or if any of the methods or chemicals proposed by the
Water Treatment Specialist present potential problems or hazards
to the equipment supplied.

Preliminary Checks
Prior to carrying out cleaning or chemical treatment
process, we ensure that all foreign matter is removed, and that
certified pressure tests have been carried out in the parts
of the system to be cleaned. We carry out further pressure tests
on the isolated sections of the system independently.
To comply with instruction we ensure that circulation
has been demonstrated and approval gained on all the parts of
the system, leave fully open all valves other than those used
to isolate sections. We carry out balancing and certification
after the flushing, cleaning and passivation operations. We
may also ensure that no damage can occur to any item of plant
or equipment due to cleaning and chemical processes, that chemicals
used are compatible with system materials, and that all items
of plant and equipment subject to damage or blockage due to
cleaning and chemical treatment processes are isolated or removed.
All strainers are cleaned out once during flushing
and again after the flushing operation is complete.
We comply with all requirements of COSHH regulations
during the chemical cleaning and chemical treatment of the system,
and where required by the local Water Authority, can provide
effluent tanks for storage of all waste products of cleaning
and chemical treatment processes. Following local Water Authority
approval we either neutralise and dispose to drain of all waste
produces, or ensure authorised disposal at registered sites.

Flushing
HES carries out pre-commisioning
and flushing to BS7593 for LPHW and chilled water systems.
The whole of our flushing, cleaning and water treatment procedures
comply fully with BSRIA Application Guides 8/91, Pre-commissioning
Cleaning of Water Systems, and 2/93, Water Treatment for Building
Services Systems.
All systems are flushed in accordance with documents
specified.
Flushing is undertaken, using portable equipment
if necessary, to achieve a full dynamic flush.

Cleaning and Water Treatment,
Heating and Chilled Water Systems
Water treatment consists of two separate stages,
the exact requirements being as recommended by specialist water
treatment equipment and chemical manufacturers, on the basis
of our water analysis.
The first stage treatment follows the flushing
indicated above, the system then being chemically cleaned using
a sequestrant anti-foulant, or alkaline based solutions, acceptable
to the NRA and local water authority, having a PH value between
5 and 10.
The second stage consists of a combined corrosion
inhibitor and anti-biological fouling agent being introduced.
Cleaning and Sterilisation,
Domestic Systems
After completion of the flushing process, the
systems are sterilised in accordance with BS 6700 and Health
and Safety Executive guidance notes HS(G) 70, ensuring prior
to sterilisation that systems have been flushed, cleaned and
drained.
Temporary connections necessary to permit introduction
of sterilisation chemicals and fluids should be provided, including
a 22mm valved drain connection on the incoming main immediately
downstream of the mains isolating valve. Once chemicals have
been introduced , the systems are left standing for 24 hours
and then repeatedly flushed with clean water until all traces
of chlorine have been removed. Prior to handover, samples are
taken to provide a certificate of conformity.
After chlorination of mains and cold water systems,
samples are taken to be analysed and cultured. Duplicate copies
of certificates of acceptance as drinking water are provided.
Sterilisation of systems includes all equipment
containing stored water.

Documentation
On completion of all cleaning and treatment operations,
certificates and documents are issued detailing the exact works
undertaken, together with details of all chemicals used, conditions
in which the systems have been left, and recommendations for
future system treatment. Further copies of these documents should
then be incorporated into the O&M manuals.

|